                    1.       Hi , I am trying to procure servers for a project and I wish to track them for the life of the project..
                                     I have taken these steps & questions are high lighted:
- Create a requisition in iProcurement with project (POET) information and destination type is expense
 - How to set the destination type to Inventory and still be able to add project POET information?
 - Run auto create to create PO
 - Receive against this PO
 - Run PRC: Interface Supplier Costs
 - Costs not seen in PA
 - Possibly create misc transactions and Issue the cost to inventory?
 - How to do all this from project Manufacturing?
 