Creare negative cost component (variable)
Hi!We would like to add a negative cost component on an actual cost work order (cost type 02) as some of the product is expensed as part of a reclassification from one item number to anoher
I have tried to add negative machine/labour hours but R31802A treats all amounts as positive
example:
We want to use 1 component fo each parent and expense 10 USD (done manually after mfg accounting)
Parent item = 123
comp item = 987, cost 50 USD
Routing C3 cost type, rate is 1 USD per hour, entered -10 hours on routing sheet (so it should be -10 USD per unit)
so the end result would be
I have tried to add negative machine/labour hours but R31802A treats all amounts as positive
example:
We want to use 1 component fo each parent and expense 10 USD (done manually after mfg accounting)
Parent item = 123
comp item = 987, cost 50 USD
Routing C3 cost type, rate is 1 USD per hour, entered -10 hours on routing sheet (so it should be -10 USD per unit)
so the end result would be