AIP replacement of Receipt to Availability Lead Time (RALT / WRALT) with Delivery-day Demand Percent
- DDP can be manually entered in Data Management, loaded, or for stores calculated.
- For warehouses, DDP is limited to either 0% or 100%.
- To migrate directly from (W)RALT to DDP you will take the opposite of (W)RALT and populate DDP. When (W)RALT was 0 days 100% of the day’s demand was met by a receipt therefore DDP will be 100%. When (W)RALT was 1 day 0% of a day’s demand was met by a receipt on that day therefore DDP will be 0%.