We have a requirement as a result of an audit funding. Engineers submit their timecards using Oracle Time and Labor module.

Upon inputing times they ensure the total number of hours worked is equals to 40 hours. In reality they might have worked 60 hours a week, but due to contractual agreements and labor rules they prorate hours to 40. The audit wants to see how do engineers prorate. Is there a way to capture the actual hours in OTL and use formulas to prorate hours to make it 40.

Example:                   Mon Tue Wed Thu Fri                   Total

Actual hours worked   15    15   10   10    10                   60  Hours

Prorated hours           10     10   6.66   6.66  6.66                40  Hours

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center