Resource Profiles
The only way I have been able to do this is to create a "shadow" resource for the Forecast Projects. The trouble with this is I have double the resource availability because I have doubled the resource.
Is there a way to produce a histogram in P6 that fulfills the requirements above IE A Histogram that identifies Firm and forecast for the given resources
The Firm work and Forecast work are assigned to separate EPS Nodes.
Thanks to all who have taken the time to view this question, but can I assume that Oracle do not have a solution to this?