Resource Profiles

edited Jun 14, 2012 2:03AM in Primavera (MOSC) Question
I want to produce single Stacked Labour Resource Histograms that show usage on Firm work and forecast work (Projects).

The only way I have been able to do this is to create a "shadow" resource for the Forecast Projects.  The trouble with this is I have double the resource availability because I have doubled the resource.

Is there a way to produce a histogram in P6 that fulfills the requirements above IE A Histogram that identifies Firm and forecast for the given resources

The Firm work and Forecast work are assigned to separate EPS Nodes.

Thanks to all who have taken the time to view this question,  but can I assume that Oracle do not have a solution to this?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center