Material Overhead cost not relieved when Jon completed

edited Jun 26, 2012 12:08AM in Discrete Manufacturing - EBS (MOSC) 2 commentsAnswered
Hello All,

On job completion, the final assembly's material overhead cost is not getting relieved.

Checking in metalink documents 883774.1 & 151281.1 confirms that material overhead will not get relieved and that would get into variance.

But we need to get MOH also relieved from WIP to finished goods just like material cost.

We are in standard costing.

Any helpful inputs are appreciated to achieve this.