Aftrnoon All

Im trying to setup budgets and actual view by Organsiation and Expenditure Type (account) From projects

I have setup a Resource Breakdown Structure and can report actuals by organisation and expenditure Type (category)

I have also setup a planning reosurce list by organisation and expenduiture type and budgeted by that resouce

However I cannot in the project repiorting screens see the Budget Figures coming through as comparison when I click Resource view

Any ideas would be most appreciated.

Graham