Job Cost Constants Set Up For Commitment Relief
I am having a small issue right now with Commitment Relief in E1 Version
9.0. Prior to 9.0, every job cost implementation I have worked on, in
the Job Cost Constants, all I had to do was set up Company 00000 and
ensure the Commitment Relief option was enabled. Only if a company DID
NOT want commitment relief did I set up the other companies by
exception. I have a plethora of clients set up this way, checked with
fellow consultants and found out they too follow this rule. Until now, I
never encountered system-related commitment relief issues (other than