Outside operation PO's

edited Jul 12, 2012 2:12AM in Manufacturing - JDE1 (MOSC) 7 commentsAnswered
Can you add multiple lines to an outside operation PO with different delivery dates?

For example you create the work order for 1,000 pcs, then go into the PO and change the first line from 1,000 to 200, and add four more lines of 200 each with different delivery dates.