Project cost issue
Hello All ;
I have receipts itemzed PO to project 100 Q unit price 10 so the project cots increased by 1000 USD but i have consumed this 100 units so i have to issuing it from store when i issued the 100 unit the project cost declined by the 100 units cost so the project become zero again!!!
any feedback how to solve this issue??
I have receipts itemzed PO to project 100 Q unit price 10 so the project cots increased by 1000 USD but i have consumed this 100 units so i have to issuing it from store when i issued the 100 unit the project cost declined by the 100 units cost so the project become zero again!!!
any feedback how to solve this issue??