Importing to 8.2 EPPM
When I import a project from 8.2 PPM to 8.2 EPPM all the dates change significantly when I re-schedule the project. The same is true going from EPPM to PPM. I have checked all the setting and they appear to be set the same. Has anyone been successful importing or exporting with the dates holding after re-scheduling?