Labour Cost Rate Extension Question
I am implementing labour transactions in Oracle Projects integrated with a third party system used to record the time.
Time will be transferred from the third party system to Oracle Projects and rates will be stored in Oracle Projects by employee or job.
We have the following requirements and we would like to use the labour cost extension to handle it:
- Employee A contractor to work 40 hours per week with associated hourly rate of $10.
- Employee A records 50 hours in Clarity in a specific week against different projects.
The requirement is to create actuals in Oracle Projects only for the contracted hours cost. This mean that we want a total of expenditure created against the employee in Oracle Projects of $400.