How to get Actuals into Forcasts
1. Created a Contract Project
2. Created an Agreement
3. Baselined Cost and Revenue Budget from Forms
4. Entered Primary Cost Forecast manually.
5. Created a Inventory PO for the Project and performed PO Receipt against the Project Locator. Import Cost to Project
6. Run Update Project and Resource Base Summaries and Update Project Performance Data.
7. Run Update Project Summary Amounts for a single project.
8. Generate Forecast. (The Generation Options are -
8a. Actual Amounts Through - Current
8b. ETC Source - Task Level Selection
8c. Plan Type- <My Forecast Budget>
8d. All the check boxes checked (Change Documents, Open Committments, Retain Manually Added Plan Lines)