P6R8.2 Auto Computing Actuals with changing Units/Time

edited Jul 24, 2012 9:46PM in Primavera (MOSC) 2 commentsAnswered ✓
Having a problem with auto-compute actuals, but I think I understand how it currently works.

When using auto-compute actuals, P6 uses Planned Units/Time to calculate the number of actual hours for the activity. Just like Apply Actuals is supposed to work, it calculates back to the start date of the activity.

However, if at the beginning of the activity the resource is 50% but later they become 100% to the activity, auto-compute won't work to translate the new estimated hours to Actual hours.

So right now it does this:

Planned U/T = 50%
Week                     1     2     3
Remaining          20   20   20  
Actual                    0     0      0

Apply Actuals for week 1

Week                    1     2     3
Remaining           0   20   20  

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center