Missing MPS/MRP Multi-Site and Multi-Level MRP messeges using BP Relationships
I have run into a situation where the client has setup multi-site planning, which I have done many times in the past.
However, they have included a complexity I haven’t seen work successfully before.
They have upstream supply plants and distribution centers 7 levels deep.
They came to me because they are able to run MRP and get messages for levels 0 through 4, but then nothing.
They are using Master Planning Families as a means to define the Item Branch Plant Relationship (P3403T) rules.
I have not been able to access their JDE 8.11 E1 system, but the BA seems very knowleadgable and has fixed levels 0 through 4.