We're on PeopleSoft 9.1 and have identified a problem with using procurement contracts. Buyers are creating adhoc PO's that have lines associated to a valid purchase order type contract, but when the PO is saved and dispatched, the process isn't updating the contract release quantities or release amounts. Contract release quantities and amounts are updating correctly when the PO is created from a requisition and processed through the PO_AUTO_SRC job, but not when the PO is directly entered. According to the PeopleBooks documentation, contract releases should be updated by either method of PO creation. Thought this might be a configuration setting of some type, but as