Phantom Baseline Data

edited Aug 23, 2012 9:58AM in Primavera (MOSC) 2 commentsAnswered
I have a schedule that I imported.  Before I even created any baselines, there is baseline information showing such as variance to BL1 Start and the primary baseline bars are showing on the Gant chart.  In the Assign Baselines window the Project Baseline is set as <Current Project> as is the Primary Baseline selection.

How can I have different information when there is nothing to which it can be compared?