Hi,
I am working in Project Management Module. For any given project, I go to "Tasks" in "Workplan" tab and then select the action "mass update progress".
Then I try to update the "actual to date" quantity (attachment 1: updating actual to date quantity for task "experiment 1" to 50). Then I select the "apply and continue updating" option and an error comes as follows:

"You can enter actual effort only if you have enabled effort collection for the project and task 149171". (refer attachment 2)

How can I get rid of this error and successfully update the actual to date quantity?

Thanks and Regards,

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center