Hi,
I am working in Project Management Module. For any given project, I go to "Tasks" in "Workplan" tab and then select the action "mass update progress".
Then I try to update the "actual to date" quantity (attachment 1: updating actual to date quantity for task "experiment 1" to 50). Then I select the "apply and continue updating" option and an error comes as follows:
"You can enter actual effort only if you have enabled effort collection for the project and task 149171". (refer attachment 2)
How can I get rid of this error and successfully update the actual to date quantity?
Thanks and Regards,
I am working in Project Management Module. For any given project, I go to "Tasks" in "Workplan" tab and then select the action "mass update progress".
Then I try to update the "actual to date" quantity (attachment 1: updating actual to date quantity for task "experiment 1" to 50). Then I select the "apply and continue updating" option and an error comes as follows:
"You can enter actual effort only if you have enabled effort collection for the project and task 149171". (refer attachment 2)
How can I get rid of this error and successfully update the actual to date quantity?