Requirement to change setting so capitalised lines interfaced from PA to FA mass additions with stat
Clarification of requirement
Thanks for the response. It is not that we want to keep assets on hold, we just want to control when the lines are picked up by the post mass addition process. We are currently changing the status immediately it reaches mass additions. However, with a large department operating in this area, there is potential for mass additions to slip through.
We would therefore like a solution that is not reliant on manual operation and which has the capital project lines interface to mass additions in a status that is not picked up by Post Mass Additions until we are ready.