Hierarchy load job failes sometime due to PNI Buffer exception(RPAS - V13.1.2.36) . We use workaround as follow:
- Delete all buffer position using dimensionMgr by setting minpct and maxpct to 0.
- Re-add buffer position using dimensionMgr by setting minpct and maxpct to some optimal value.
- Restart hierarchy load job.
Problem with this fix is that it takes around 5 to 6 hours to delete and add buffer position. After that we start hierarchy load, which runs around 5 to 6 hours. So whenever this failure happens, we are not able to complete batch jobs within time window.
Error Detail:
====================================================================================================================
<E 2012Sep07 19:13:10.238>
<E 2012Sep07 19:13:10.238> loadHier failed on domain: /if/r1/rdf/rpas_base/domains/Wag_RDF