P6 Prof 8.2 Schedule a Project - more detailed definition
When I read the documentation, it says that Schedule a Project will cascade duration changes etc. But when I change the duration of a critical path acitvity in the Activities view and click SAVE, the dates automatically cascade. So what else does the on-demand job do to schedule a project?