Reversing Task Status to In Progress from Completed
1. We are unable to revert Task Status to 'In Progress' once updated to 'Completed'.
Our next allowable status setup says All. Please share with us how to avhieve the above.
2. Another issue faced is, when changing Top Task status from In Progress to Completed, all sub tasks are also updated as Completed. Further, when Top Task staus is changed from Completed to anoher staus Closed (system status being Completed), sub tasks are not updated to Closed. Is this is the correct functionality or are we missing any setups?
Please do share your thoughts