Batch Replan for Dependent Demand-MRP
We are a manufacturing company and we are running multiple MPS and MRP runs on a daily basis. Recently, we have a need of utilizing "simulations" feature in ASCP when some temporary finished goods demands are anticipated.
Our finished goods and intermediates are MPS planned whereas raw materials are MRP planned. We were able to do batch replan for finished goods entering manual demand in the workbench. However,
batch replan is not possible for MRP since dependent demand can not be entered manually in the workbench ( becoz intermediates & FG are MPS planning control).
Can anyone suggest options to handle this? What we are looking for a raw material incremental recommendation quantity for an expected demand of FG.