Hi, The Scenario is like this
I have an equipment which needs monthly maintenance(Service Type: 1ASSOC) & Quarterly maintenance (Service Type: 2ASSOC)
The association setup I did is as follows
1. PM Schedule Definition of the Two service Types with Service Interval days, Model Order & Multiple WO field with "1"
2. Selected the 2ASSOC (as primary) and from row exit I have added the association with the following details
Service type: 1ASSOC
Threshold %: 100
Threshold hrs: -Blank
Work order: "2" Combine Work Order
Work order status: -Blank.
While I am updating Schedule I had 2 orders. Please advise whether my Set up is right or not.
I have an equipment which needs monthly maintenance(Service Type: 1ASSOC) & Quarterly maintenance (Service Type: 2ASSOC)
The association setup I did is as follows
1. PM Schedule Definition of the Two service Types with Service Interval days, Model Order & Multiple WO field with "1"
2. Selected the 2ASSOC (as primary) and from row exit I have added the association with the following details
Service type: 1ASSOC
Threshold %: 100
Threshold hrs: -Blank
Work order: "2" Combine Work Order
Work order status: -Blank.
While I am updating Schedule I had 2 orders. Please advise whether my Set up is right or not.