‘Miscellaneous Issue to Project’ and ‘miscellaneous receipt from Project’
I am processing a transaction in Inventory for ‘Miscellaneous Issue to Project’ and ‘miscellaneous receipt from Project’. The steps followed are -
Miscellaneous Issue to Project -
· N> Transaction> Miscellaneous Transaction> eIB Misc. Issue to Project (User defined)
· Project number is given in the 'Source Project' field and not at the locator level.
· Accounting Close cycle> Project Cost Transfers> Cost Collection Manager.
· In the Projects responsibility, run the Transaction Import and Import the cost to Projects.
Miscellaneous receipt from Project -
· N> Transaction> Miscellaneous Transaction> eIB Misc. Receipt from Project (User defined)
· Project number is given in the 'Source Project' field and not at the locator level.