Global change incurs UDF indicator icons to change to text
Hi quick question; how to retain the indicator icons using a global change if statementI am running a standalone - Primavera P6 Project Management with an oracle database, patched to SP3.The issue as I see it is; a global change incurs all UDF indicator icons to change from its original "icon" image to text.Process I have used is as follows; Creation of a User Defined Field as an "Indicator" Selected red indicator icon for project float <= 0 Created a global change IF statement, if total float is <=0 then use the red indicator icon Post global change the indicator was n