How does one enter a project budget?
We have been on Oracle Projects for over a year; we are on EBS 12.1.3. Up to this point, we have never entered Project budgets or forecast. Now our user is wanting to enter Project budgets.
On a test instance, I navigate to Projects Super User > Budgets. I query an existing project number and select budget type= “Approved Cost Budget”. When I press the Tab key or click any other field on the Budgets form, PAXBUEBU, I get error message, “An approved cost budget plan type exist for this project. You can create new versions only for the corresponding plan type.” By the way, the project# I chose is a billable project type.