Why Purchase Orders that are cancelled still add up to the project encumbrance total.

edited Feb 28, 2013 7:23AM in Supply Chain Management - PSFT (MOSC) 5 commentsAnswered
WHY Purchase Orders that are cancelled still add up to the project encumbrance total?

EXAMPLE 1.
1.  07/23/12 A requisition is created with project lines (Req XXX:  1 line for $1,500.00)
2.  07/23/12 requisition XXX is approved.
3.  07/23/12 The requisition sources to a purchase order with project lines (PO YYY: 1 line for $1,500.00)
      This purchase order also has a contract Z

4.  07/24/12 A change order is done cancelling the purchase order (no receipt or voucher activity is on the purchase order).
5.  The PO encumbrance amount remains on the Project Valuation screen and on the Activity Valuation (tab).
       NAVIGATION:  Project Costing > Project Definitions > General Information > Search Project ID CCLRTSFA08
       > Project Valuation (link) > Search Project ID CCLRTSFA08  > COMPARE TO BUDGET (link)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center