When on hand quantity is not there system needs to generate a PR
When on hand quantity is not there system needs to generate a PR based on the Manufacturing Pick Move Order issued by eAM Work Order Release.
Fix
Until R12.1 MRP (Material Requirements Planning) was able to create PRs automatically based on demand but MRP has been obsoleted. ASCP (Advanced Supply Chain Planning) can fulfill your requirement (crate purchase requisitions based on EAM work orders demands) however, this is a module has separate license (if not used yet) and requires complex setup.
Question
What are the setup steps for ASCP to make this work?