Applying 11.5.10 Pre-Upgrade Patches Far in Advance
Good Afternoon,
While running upgrade cycles going from 11.5.10 to 12.1.3, we've decided we would like to apply the pre-upgrade 11.5.10 patches to production now, so they're already there when we move forward with future upgrade cycles and the actual production upgrade. This will save us time on test cycles, and shorten our downtime window by an hour or two.
Has anybody else done this? Any thoughts on the viability of running production with these patches for ~6 months prior to the actual upgrade?
The list of patches we've identified for 11.5.10 are:
4685497
5259121
4684603
8845395
9685457
5233248
9889680
6980384
8904721
8910899
10231107
5760729
Thanks!
Rob
Tagged:
0