Forecast PM Work Orders fails for schedule definition that establishes wo creation when meter readin
The forecast program failed to generate a work order when the meter reading exceed the interval, my setup was:
1. I did setup a meter with number of past readings equal to 999999 and rate per day of 1with initial reading of 0.
2. Schedule defintion with a base meter and a interval of 5000.
3. I have entered a meter reading in the html page for mass meter readings with an absolute value of 6000.
4. I ran the forecast program for the specific asset and it didn´t show any suggested WO, the I have ran the program of generate work orders and it didn´t generate the WO.