Query on Multi faciliy MPS with G rule
We are working in E9.1 and using G rule for our MPS planning with forecast and sales order as sources of demand. The businss scenario is
- first 3 months only confirmed sales order , with W type work orders.
- next 6 months rolling forecast records (weekly)
Defined planning rule as G, planning fence as 90 days and message display as 180 days.
There will be an overlap both forecast & sales records during first 90 days periods also. Let us assume the following demand scenario
- SO demand of 1000 qty on 16 Nov, and forecast qty of 1000 qty on 16 Nov
- SO demand of 2000 qty on 23 Nov, and forecast qty of 2500 qty on 22 Nov.