PJC : Pre approved batches (Usages and misc. transactions cost) not performing budgets controls
Pre-approved batches (Usages and misc. transactions cost) not performing budgets controls. because it accepting more than budget amount. But if we see Project status inquiry its showing accurate actual & budget balances. But why it not stops, if user entering more that budget amount.
We want know will it work budget control for Pre-approved batches ???
Budgets we have define with in the projects there is no integration with GL. But we are unable to get fund checks for pre-approved batches. But PO level its working fine.
Please help us to resolve.