How to create 2 or more planned orders for 1 forecast date ?
Current situation:I have forecast with only 1 date (for example, 30-Nov-2012).
Forecast item_1 is making, it uses resource_1. Resource_1 has capacity constraint: only 6 hours every day from 10-00 to 16-00.
Forecast quantity for item_1 = 9 tons for 30-Nov-2012 (it needs 9 hours of Resource_1).
Now I get 1 planned order in ASCP (constrained plan):
start date = 29-Nov-2012 13-00
finish date = 30-Nov-2012 16-00
But I want to get 2 separate orders for every day:
first
start date = 29-Nov-2012 13-00
finish date = 29-Nov-2012 16-00
second
start date = 30-Nov-2012 10-00
finish date = 30-Nov-2012 16-00
Is it possible?
Forecast item_1 is making, it uses resource_1. Resource_1 has capacity constraint: only 6 hours every day from 10-00 to 16-00.
Forecast quantity for item_1 = 9 tons for 30-Nov-2012 (it needs 9 hours of Resource_1).
Now I get 1 planned order in ASCP (constrained plan):
start date = 29-Nov-2012 13-00
finish date = 30-Nov-2012 16-00
But I want to get 2 separate orders for every day:
first
start date = 29-Nov-2012 13-00
finish date = 29-Nov-2012 16-00
second
start date = 30-Nov-2012 10-00
finish date = 30-Nov-2012 16-00
Is it possible?
0