When importing activity relationships into a P6 schedule with out any existing logic and or relationships (activity data was also imported from excel) I get an error message "import did not complete successfully"

After reviewing the imported realtionships I find that all Start to Start and Finish to Finish relationships have been replaced with Finiish to Start Relationships.

For example an activity with a Start to Start of 20 has  been replaced with a Finish to Start of 20