importing activity codes (project level) from excel to P6
Please note the schedule that i am working with is recreation of a P3 schedule and I have succesfully imported the activity data and logic with the exception of manually changing some of the relationships back to Start to Starts and Finish to Finish (an issue i noted in a previous post)