Not sure why I am  so many issues with importing from excel to p6 but i am now trying to import  actvity codes (project level and not global or EPS)  into P6, the message indicated that the import was successful, however the codes are not  assinged  to the actvities.

Please note the schedule that i am working with  is recreation of a P3 schedule and I have succesfully imported the activity data and logic with the exception of manually changing some of the relationships back to Start to Starts and Finish to Finish (an issue i noted in a previous post)