Why MRP workbench shows additional demand when WIP job order is released from MPS workbench?

edited Nov 29, 2012 6:14AM in Value Chain Planning - EBS (MOSC) 4 commentsAnswered ✓
Consider following scenarioItem A is FG which requires raw materials B, C & D
After running MRP for Item A system suggests demand for Item B, C & D
If I release requisition for Item B from MRP workbench & then release WIP Job order for item A from MPS workbewnch.
In this case when I am viewing MRP workbench then it shows demand as follows
Item            Qty          Action         Order Number
B                 -1           Demand        WIP Job no.
C                -1            Demand        WIP Job no.
C                -1            Demand       
D               -1             Demand        WIP Job no. 
D                -1            Demand                               ................(Demand should be for 1 Qty only) 
C                2             Release                                                  

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center