Importing Activity Codes from Excel Not Possible in P6 R8.2 and work around??
As a work around and since i had to code approximatley 999 activities with (64) different code values I decided to create a UDF for the codes and then exported a template to excel.
I then copied the activities codes (from a spreadsheet developed from a P3 file) into the exported UDF which successfully imported back into P6
Then I used the global change to code all 999 activities, problem is i had to do 64 codes, one by one in global change for example,