PJC : PSI window unable to show Actuals and budget balances

edited Dec 12, 2012 11:04PM in Projects - EBS (MOSC) 3 commentsAnswered
Dear All,

We have projects along with budgets. For this project we have created PO à Commitments interfaced àafter running PRC: Update project summary amounts, PSI window, it shown commitments then budget also showed after deduction of commitment.

After that Receipt & Invoice also created (accrual at receipt enabled) à Run PRC: PRC: Interface supplier costs à Cost interfaced but PSI window not showing the actual and budget balances (Expenditure  inquiry window showing cost expenditures).

Issue -1à PSI window not showing the actual and budget balances (showing full budget amount).

Issue-2à Supplier details not showing in expenditure window. When we select  from Project expenditures items

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center