Phantom Resource Assignments Appear in Schedule

edited Dec 12, 2012 5:56AM in Primavera (MOSC) 1 commentAnswered
Experiencing an issue that I have not seen before. We transferred a schedule between database instances using an XER, and although we do not know if the issues started to occur right after the import, we did begin to notice several resource assignments were added to activities to which they did not belong. All new resource assignments had budgeted units equal to original duration x default units/time. We did not perform any resource assignment imports via excel in the period between the XER import and the discovery of the issue. Any one else experience this before?

Running P6 V7.0 on a SQL DB.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center