Planned Orders with 1 qty
Hi ,
We are an OPM org integrated with ASCP. i have an issue with the creation of the planned order.
when there is decimal requirement, we are getting a two planned orders, one for the whole number and other for the decimal value alone.
For Ex: If the requirement for the item is 10589.34, then ASCP recommends two separate planned order as 10589 qty and 1 qty.
When i set the profile option to MSO: Enable Decision rules to No , then the planned order appears as expected 10590 qty. Rounding Qty in item attributes is checked in both cases.
I am not able to understand the root cause of the issue and the solution is also different.
We are an OPM org integrated with ASCP. i have an issue with the creation of the planned order.
when there is decimal requirement, we are getting a two planned orders, one for the whole number and other for the decimal value alone.
For Ex: If the requirement for the item is 10589.34, then ASCP recommends two separate planned order as 10589 qty and 1 qty.
When i set the profile option to MSO: Enable Decision rules to No , then the planned order appears as expected 10590 qty. Rounding Qty in item attributes is checked in both cases.
I am not able to understand the root cause of the issue and the solution is also different.
0