MRP : Starting date calculation of a planned discrete job

edited Dec 23, 2012 6:51PM in Discrete Manufacturing - EBS (MOSC) 3 commentsAnswered
Hi,
I need to have some precision about MRP calculation in ebs 11i. Discrete manufacturing.
Take two manufactured item M1 and M2.
M2 is a component of M1 ( 1 M1 = 2 M2).

Suppose variable lead time of M1 is 2 days and M2's is 3days. suppose you have no inventory for M1 and M2.
if you have a need (forecast for example) of 100 units of M1 with needed date 31/12/12, what would be the start day of the planned discrete job of M1 ? What about so the start date of the planned discrete job of M2 ?

Regards.