Copy bill can not copy component item with scheduled ECO
SR:3-6593776901version: R12.1.2
The issue can be reproduced as following:
1. Create scheduled ECO “PAO90” for assembly item “FG01”
Effective date:01-Mar-2013, Status:Scheduled
Action: add component:3B55-10000AZ
2.check bills of material for FG01
uncheck Implemented Only, found the item 3B55-10000AZ show on the bill with Implemented Unchecked.
3.Copy the bills from FG01 TO FG03 from Bills of material Form>tools>copy bill from,
copy option :Future and Current
4.Check the bom structure for item FG03,
uncheck Implemented Only, found the item 3B55-10000AZ is NOT shown on the bill.
Hence the question here is:
The issue can be reproduced as following:
1. Create scheduled ECO “PAO90” for assembly item “FG01”
Effective date:01-Mar-2013, Status:Scheduled
Action: add component:3B55-10000AZ
2.check bills of material for FG01
uncheck Implemented Only, found the item 3B55-10000AZ show on the bill with Implemented Unchecked.
3.Copy the bills from FG01 TO FG03 from Bills of material Form>tools>copy bill from,
copy option :Future and Current
4.Check the bom structure for item FG03,
uncheck Implemented Only, found the item 3B55-10000AZ is NOT shown on the bill.
Hence the question here is:
0