Completion date on Saturday 00:00:00

edited Dec 26, 2012 10:04PM in Discrete Manufacturing - EBS (MOSC) 3 commentsAnswered
Hi,
 This is 11i instance.

1. Create a DJ by manual.
2. Start date=20-DEC-2012 00:00:00, save,.
3. Assembly leadtime=7 days
4.WIP will auto calculate completion date = 29-DEC-2012 00:00:00

29-DEC-2012 is saturday that non-workday on calendar

Customer expected completion date=31-DEC-2012 00:00:00.

If DJ generate from ASCP, then completion date=31-DEC-2012 00:00:00.

Customer confuse the discrete job completion date.



Kind Regards,
Andy Sun
Oracle Support Services.