Completion date on Saturday 00:00:00
Hi,
This is 11i instance.
1. Create a DJ by manual.
2. Start date=20-DEC-2012 00:00:00, save,.
3. Assembly leadtime=7 days
4.WIP will auto calculate completion date = 29-DEC-2012 00:00:00
29-DEC-2012 is saturday that non-workday on calendar
Customer expected completion date=31-DEC-2012 00:00:00.
If DJ generate from ASCP, then completion date=31-DEC-2012 00:00:00.
Customer confuse the discrete job completion date.
Kind Regards,
Andy Sun
Oracle Support Services.