OPM/INV (master data) > ASCP (planned order suggestion) > PS (planned order detail scheduling) > OPM
The customer wants to have multiple planned orders for Item A suggested by ASCP (and then scheduled by PS) every time the demand exceeds supply for the item.Each of resulting OPM batches should be created for a quantity that is valid in terms of Recipe Validation Rules.
There should be minimum amount of batches created i.e. the Validation Rule for the biggest batch size should be taken.
The overal supply (number of batches multiplied by each batch quantity) should be equal to value prescribed for the item A.
Example:
There is a Recipe Validation Rule that allows to create a batch for 100 EA, 200 EA, or 400 EA of Item A
There should be minimum amount of batches created i.e. the Validation Rule for the biggest batch size should be taken.
The overal supply (number of batches multiplied by each batch quantity) should be equal to value prescribed for the item A.
Example:
There is a Recipe Validation Rule that allows to create a batch for 100 EA, 200 EA, or 400 EA of Item A