Cost Rollup for a new Parent Item PA1, where BOM effective date is future date
Hi,
I am looking for some help on Cost rollup (Cost Freeze). Let me try to explain the issue.
I am having a Parent Item PA1 with bill of materials as below with PA2 and PA3 in 2nd, 3rd level, Where the effective date starts from 01/03/2013.
Level2nd Item NumberDescriptionQtyUMSTKTLNTYEffective FromEffective ThruParent Item1PA2BEEF BACON SMOKED1KGMN01/03/201331/12/2040PA1.2C01BEEF1KGPS01/03/201331/12/2040PA2.2PA3BEEF BACON SLICED1KGMN01/03/201331/12/2040PA2..3C02CHICKEN1KGPS01/03/201331/12/2040PA3.2C02CHICKEN1KGPS01/03/201331/12/2040PA21C01BEEF1KGPS