Lead time level and manufacturing lead time is not considered while part-list creation
Hello
I have following set up -
Child item with lead time level and manufacturing lead time = 2 days.
Parent item = no lead time
When I am creating Rate for parent item - in partlist I can see requested date of rate/ Parent item = requested date of Child item.
I used R31410 to attach partlist, as well I tried attaching BOM manually.
I expect requested date in part-list less than by 2 days than Requested date in rate.
Thanks for clarification.
Rohit
0