Lead time percentage calculate
12.1.2
Routing set up as following:
1. All resources are available 24 hours
2. department01 seq=10 resource01 uom=min basis=item usage=20 assingned units=1 schedule=yes
department02 seq=10 resource02 uom=min basis=lot usage=30 assingned units=2 schedule=yes
department03 seq=10 resource03 uom=min basis=item usage=100 assingned units=4 schedule=prior
department03 seq=20 resource04 uom=min basis=item usage=50 assingned units=5 aschedule=yes
3. Run 'Calculate Manufacturing Lead Times GUI ' for this routing, result as following:
Seq Leadtime%
10 0
20 94.38
30 92.13
40 97.75
How is the leadtime calculate?
Thanks
Fengling