Hi,
Scnerio MY ATO Model having 10 components out out ot 10, 4 are MRP planned components but ATO Model is not MRP planned.
Now i have created as sales Order progress the Order it created the JOB for * Item.

Now i have submitted the MDS and MRP.
Now in MRP work bench i am getting the 4 components as a demand.

Regards,