Hi,
i have created a ATO model item with out MRP planned and.
i have created the BOM for ATO Model and it is having 10 components out of 10, 4 are MRP planned
components.
Booked the Sales Order and Progressed the Order it has creaed a JOB for ATO Item.
Now i submitted MDS and MRP.
I MRP Work bench it si suggestig the 4 Components as a Demand.
Customer dont want the see the as deamd in MRP work bench when the parent item is not MRP planned.
Kindly suggest.
i have created a ATO model item with out MRP planned and.
i have created the BOM for ATO Model and it is having 10 components out of 10, 4 are MRP planned
components.
Booked the Sales Order and Progressed the Order it has creaed a JOB for ATO Item.
Now i submitted MDS and MRP.
I MRP Work bench it si suggestig the 4 Components as a Demand.
Customer dont want the see the as deamd in MRP work bench when the parent item is not MRP planned.
Kindly suggest.